Name of Work
: |
Construction of bridge across river Damanganga connecting Nani Daman and Moti Daman. |
| |
| Client : |
National Highway Division, Bharuch. |
| |
| Cost of Work : |
Rs.341.5 Million. |
| |
| Year of Completion : |
Work in Progress |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of Railway bridge across river Narmada near Jabalpur on Gondia Jabalpur gauge conversion project. |
|
| |
| Client : |
South East Central Railway, Bilaspur. |
| |
| Cost of Work : |
Rs.350.59 Million |
| |
| Year of Completion : |
Work in Progress |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Design and Construction of bridge across Godavari river on Ahmednagar Aurangabad section. |
| |
| Client : |
Keti Sangam Infrastructure (I) Ltd., Indore.
A work of PWD, Mahrashtra.
|
| |
| Cost of Work : |
Rs.115 Million. |
| |
| Year of Completion : |
Work in Progress |
| |
|
|
| |
|
| |
| Name of Work
: |
Design and Construction of ROB on DCM Railway Crossing at Kota, Rajasthan. |
|
| |
| Client : |
Urban Improvement Trust, Kota |
| |
| Cost of Work : |
Rs.195.3 Million. |
| |
| Year of Completion : |
Work in Progress |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of minor bridge near Varkund at Daman. |
| |
| Client : |
Omnibus Industrial Development Corporation Ltd., Daman. |
| |
| Cost of Work : |
Rs.16.2 Million. |
| |
| Year of Completion : |
Work in Progress |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of four lane bridge across river Sabarmati connecting Vasna Pirana on 120 feet road at Ahmedabad. |
|
| |
| Client : |
Ahmedabad Municipal Corporation, Ahmedabad. |
| |
| Cost of Work : |
Rs. 281.51 Million |
| |
| Year of Completion : |
December 2006 (completed in a period of 19 months against allotted time period of 24 months i.e. ahead of schedule by 5 months) |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Providing Bridge No. 33, 34, 35 between Stations Bhilupur and Thuwavi in connection with Gauge Conversion work of Pratapnagar - Chota Udepur. |
| |
| Client : |
Western Railway, Pratapnagar, Vadodara. |
| |
| Cost of Work : |
Rs.53.3 Million. |
| |
| Year of Completion : |
August 2007. |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of elevated road
including approach roads connecting the existing
road on Dadabari side and the road going to
Garh Palace by passing Kishorepura Gate on
Chambal River reservoir near the barrage at
Kota, Rajasthan. |
|
| |
| Client : |
Urban Improvement Trust, Kota. |
| |
| Cost of Work : |
Rs. 43.48 Million |
| |
| Year of Completion : |
March 2006 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of Panvel Creek
Bridge (Foundation and Substructure). |
| |
| Client : |
B. G. Shirke Construction Technology Ltd.,
Pune |
| |
| Cost of Work : |
Rs. 107.51 Million (excl. cost of material) |
| |
| Year of Completion : |
December 2006 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of Road over Bridge
near Railway Culvert No. 436 on Dindoli Udhna
Industrial Estate Road, Surat. |
|
| |
| Client : |
Surat Municipal Corporation, Muglisara,
Surat. |
| |
| Cost of Work : |
Rs. 100.5 Million |
| |
| Year of Completion : |
October 2006 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of Road over Bridge
on Borkhera Anantpura Bypass Road at Kota. |
| |
| Client : |
Rajasthan Urban Infrastructure Development
Project, Rajasthan
|
| |
| Cost of Work : |
Rs. 111.7 Million |
| |
| Year of Completion : |
June 2005 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of ROB at Mandore
Railway Station, on lieu of L.C. No. C-11,
Jodhpur. |
|
| |
| Client : |
Rajasthan Urban Infrastructure Development
Project, Rajasthan
|
| |
| Cost of Work : |
Rs. 58.3 Millions |
| |
| Year of Completion : |
December 2003 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of ROB near Basni
Indl. Area, in lieu of L.C. No. C-206, Jodhpur. |
| |
| Client : |
Rajasthan Urban Infrastructure Development
Project, Rajasthan
|
| |
| Cost of Work : |
Rs. 48.8 Millions |
| |
| Year of Completion : |
January 2004 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of Flyover at Chhawani
Circle at Kota, Rajasthan. |
|
| |
| Client : |
Rajasthan Urban Infrastructure Development
Project, Rajasthan |
| |
| Cost of Work : |
Rs. 72.70 Millions |
| |
| Year of Completion : |
September 2003 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of High Level Bridge
across river Tapi Burhanpur, M. P. |
| |
| Client : |
Ashoka Buildcon Ltd., Nashik
|
| |
| Cost of Work : |
Rs. 58.5 Millions |
| |
| Year of Completion : |
December 2003 |
| |
|
|
| |
|
| |
| Name of Work
: |
Design and Construction of ROB
in lieu of L.C. No. 259/A (Spl.) on Chikhodara
- Anand - Sojitra Road on Ahmedabad - Vadodara
section of Western Railway. |
|
| |
| Client : |
Western Railway, Mumbai |
| |
| Cost of Work : |
Rs. 24.4 Millions |
| |
| Year of Completion : |
May 2003 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Design and Construction of six
lane ROB in lieu of L.C. No. 4A on Kalol Katosan
MG Railway on Ahmedabad Mehsana Road Project.
(in JV) |
| |
| Client : |
Ahmedabad - Mehsana Toll Road Co. Ltd.,
Ahmedabad. |
| |
| Cost of Work : |
Rs. 124.00 Millions |
| |
| Year of Completion : |
September 2002 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of high level bridge
across river Tapti near Nana Varachha, Surat |
|
| |
| Client : |
Surat Municipal Corporation, Surat |
| |
| Cost of Work : |
Rs. 202.00 Millions |
| |
| Year of Completion : |
June 2001 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of foundation,
sub structure, super structure and approach
road in connection with ROB at Nalasopara,
Mumbai for MSRDC. |
| |
| Client : |
IRCON International Limited, Mumbai. |
| |
| Cost of Work : |
Rs. 84.10 Millions |
| |
| Year of Completion : |
September 2000 |
| |
|
|
| |
|
| |
| Name of Work
: |
Design & Construction of
Mandsaur Bye pass Bridges at 4/4 Km 6/4, Km
& 7/6 Km |
|
| |
| Client : |
Prakash Asphaltings & Toll Highways
(I) Ltd, Indore (M.P.) |
| |
| Cost of Work : |
Rs. 13.1 Millions |
| |
| Year of Completion : |
June 1998 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Design & Construction of
Road Over Bridge in lieu of L.C. at Km.11/13-14
between Chalthan, Gangadhra near Surat. |
| |
| Client : |
Ashvika Construction Pvt. Ltd., Vadodara
|
| |
| Cost of Work : |
Rs. 15 Millions |
| |
| Year of Completion : |
January 1998 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of Flyover Bridge
at Athwagate Junction Surat. |
|
| |
| Client : |
City Engineer (SMC), SURAT |
| |
| Cost of Work : |
Rs. 79.9 Millions |
| |
| Year of Completion : |
November 1997 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of low level Submersible
Bridge on River Tapti SURAT |
| |
| Client : |
City Engineer (SMC) SURAT |
| |
| Cost of Work : |
Rs. 135 Millions |
| |
| Year of Completion : |
May 1996 |
| |
|
|
| |
|
| |
| Name of Work
: |
Construction of Road Over Bridge
near Sabarmati Railway Station |
|
| |
| Client : |
The C. E. (Const.) Western Railway, Ahmedabad. |
| |
| Cost of Work : |
Rs. 28.2 Millions |
| |
| Year of Completion : |
June 1994 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Design & Construction of
New BG Railway Bridge across MAHI RIVER at
Vasad. |
| |
| Client : |
The C. E. (Const.) Western Railway, Ahmedabad. |
| |
| Cost of Work : |
Rs. 60 Millions |
| |
| Year of Completion : |
September 1993 |
| |
|
|
| |
|
| |
| Name of Work
: |
Design and construction of New
BG Railway Bridge on river SIRI near Nadiad |
|
| |
| Client : |
The C. E. (Const.) Western Railway, Ahmedabad. |
| |
| Cost of Work : |
Rs. 12 Millions |
| |
| Year of Completion : |
December 1992 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Design and construction of high
level Bridge across Gambhir river in km. 8/6
of Rao Pitham pur Road, near. Indore, M.P. |
| |
| Client : |
Infrastructure Leasing & Finance Service
Ltd., BOMBAY. |
| |
| Cost of Work : |
Rs. 9.2 Millions |
| |
| Year of Completion : |
December 1992 |
| |
|
|
| |
|
| |
| Name of Work
: |
Design and construction of Road
over Bridge in lieu level crossing no.211/B
at Miyagam- KARJAN. |
|
| |
| Client : |
The Dy. C. E (S & C) Western Railway,
VADODARA |
| |
| Cost of Work : |
Rs. 2.9 Millions |
| |
| Year of Completion : |
June 1990 |
| |
|
|
| |
|
| |
 |
Name of Work
: |
Construction of 487.5 meter
long Bridge across the creek between Ghoghala
village and Diu Town. |
| |
| Client : |
The Exe. Engineer, P. W. D., Works Division,
DIU. |
| |
| Cost of Work : |
Rs. 35 Millions |
| |
| Year of Completion : |
April 1990 |
| |
|
|
| |
|
|
| |