Vijay M. Mistry Construction Pvt. Ltd.
 
 
 
Bridges-Flyovers  
 
Name of Work : Construction of 2 two lane bridge on Surat Bardoli Road at Aai Mata junction, Surat.
 
Client : Surat Municipal Corporation, Surat.
 
Cost of Work : Rs.428 Million.
 
Year of Completion : Work in Progress
 
Description of Work :

Two nos. of two lane flyover bridges (total length 720.53 and width 8.4 m of each flyover) is consisting of

Foundation :

1200 mm dia pile

Substructure :

RCC Pier and Pier Cap

Superstructure :

18 x 20 m + 2 x 45 m (Pretensioned Precast I Girders & PSC Box)

Approaches :

300 m long R.E.structure.

 
 
Conventional Routine Load Test on Pile Pier and Pier Cap
 
Conventional Routine Load Test on Pile
Pier and Pier Cap
 
Casting of Precast Pretensioned I Girder at casting yard Prestressing of Precast I Girder at casting yard
 
Casting of Precast Pretensioned I Girder
at casting yard
Prestressing of Precast I Girder at
casting yard
   
Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes
 
Lifting and launching of Precast Pretensioned I Girder in position using two Crawler Cranes
   
Casting of PSC Box Girder Erection of RE Panel
   
Casting of PSC Box Girder Erection of RE Panel
   
 
 
Remarks :
  • The foundation of RCC bored piles (about 20 m long) were executed using MAIT HR 180 Hydraulic Rig. 144 nos. of Pretensioned Precast I Girders were cast in casting bed and launched them in position with the help of Crane. The 45 m box girders were cast in situ.

  • The stipulated construction period is 18 months. It is expected to complete the work before schedule.
© Copyright 2005, Vijay M. Mistry Construction Pvt. Ltd.  
Clients Awards & Certificates Central Store