| Name of Work
: |
Civil and Structural works for
construction of intake well and works on the
Bank for 15 MGD Water Supply Scheme for our
1050 MW combined Cycle Power Plant at village
Akhakhol, Dist. Surat. |
| |
| Client : |
Torrent Power Generation Ltd., Ahmedabad. |
| |
| Cost of Work : |
Rs. 53.5 Millions |
| |
| Year of Completion : |
Work in Progress |
| |
|
| Description of Work : |
Well : 12 M Outer Dia (8 M Inner
Dia) and 30 M depth
Approach Bridge : 5 x 30 M PSC Spans.
Foundation of Approach Bridge : 1500
mm Dia. Bored Cast in Situ Pile in a standing
water upto 7 m
Substructure : RCC
Super Structure : Prestressed Girders
and RCC Slab.
Allied works : Control Room, Security
Cabin, Road Works, 1018 Spirally welded pipe, |
|
| |
|
| |
|
View of Intake Well
|
|
|
| |
View
of Approach Bridge |
| |
|
| |
Spirally
Welded Pipe on Approach Bridge |
|
|
|
Pitching in cone shape
on left bank |
|
View
of Security Cabin |
|
| |
|
| |
| Remarks
: |
- Construction of Well (12 m outer dia and 8
M Inner Dia), 30 m deep in River Tapi.
- Approach bridge with 30 m x 5 PSC I section
Girder (150 m length) on 1500 mm dia Pile foundation
in a standing water of 7 m.
- Work also involved 1018 mm outer dia (9 mm
thick MS spirally welded) pipe, bank protection
work, pitching, pump house, walkway, security
cabin, control building, road works, etc.
|
|